Department of Public Works


Construction Updates

Superior Road - Euclid Avenue to Lee Road
CONTACTS
Contractor: Vallejo Company
(216) 741-3933
County: Ryan Maver (216) 348-3819
Brian Vigh (216) 301-9010
DATES
Start Date: 07-01-2022
Notice To Proceed Date: 07-01-2022
Completion Date:
Scheduled Completion Date: 11-30-2022
Anticipated Completion Date: 11-30-2022
AMOUNTS
Project Amount($): 2,988,925.02
Contract Award Amount($): 2,988,925.02
Estimated Cost To Completion($): $2,460,293.15
Approved Contract Increases($):
Approved Contract Decreases($):
PROGRESS

March 17, 2023

  • Traffic has been restored to normal patterns and city ordinances as of 11/30/22 for the entire project.
  • Work has ceased but project is substantially completed.
  • Corrective work including striping has begun.

 

February 6, 2023

  • Traffic has been restored to normal patterns and city ordinances as of 11/30/22 for the entire project.
  • Work has ceased but project is substantially completed.
  • Corrective work including striping will be assessed in the near future.

 

December 8, 2022

  • Traffic has been restored to normal patterns and city ordinances as of 11/30/22 for the entire project.
  • Work is currently being done from Mayfield Road to Euclid Avenue to finalize striping. Corrective work will be assessed in the near future.

 

November 8, 2022

  • One way traffic work zone has been established from Euclid Ave. to Mayfield Rd. and is maintained in both the north and southbound directions. Mayfield Road is Lee Rd., is open to normal traffic conditions.
  • Work is currently being done from Mayfield Rd. to Euclid Avenue in which casting adjustments, curb and sidewalk are being performed in preparation for surface asphalt.

 

October 3, 2022

  • One way traffic work zone has been established from Euclid Ave. to Mayfield Rd. and is maintained in both the north and southbound directions. Mayfield Road is Lee Rd., is open to normal traffic conditions.
  • Work is currently being done from Mayfield Rd. to Euclid Avenue in which casting adjustments, curb and sidewalk are being performed in preparation for surface asphalt.

 

September 9, 2022

  • One way traffic work zone has been established from Euclid Ave. to Mayfield Rd. and is maintained in both the north and southbound directions. Mayfield Road is Lee Rd., is open to normal traffic conditions.
  • Contractor has completed the asphalt and road work from Lee Rd. to Mayfield Rd. in which the road was re-opened to normal traffic.
  • Work is currently being done from Mayfield Rd. Euclid Ave. in which milling, chip and seal, and intermediate asphalt is performed.

 

August 4, 2022

  • No work zone has been established from Euclid Avenue to Mayfield Road.
  • Mayfield Road to Lee Road is closed and only open to local traffic.
  • Contractor has milled and placed intermediate asphalt from Mayfield Rd. to Lee Rd.
  • Currently working on curb/walk replacement as well as casting adjustments within the roadway.