Green Road Resurfacing - Cedar Road to Mayfield Road City of South Euclid
CONTACTS
Contractor: Perk Construction, Inc.
(440)834-1988
County: Darwin Merdes
Rich Orosz
DATES
Start Date: 01-01-2023
Notice To Proceed Date: 01-01-2023
Completion Date:
Scheduled Completion Date: 11-01-2023
Anticipated Completion Date: 11-01-2023
AMOUNTS
Project Amount($):
Contract Award Amount($): $3,554,102.65
Estimated Cost To Completion($): $3,554,102.65
Approved Contract Increases($): 0
Approved Contract Decreases($): 0
PROGRESS

March 17, 2023

  • Contractor to complete final foundation drilling for proposed signal pole located on the SW corner of Bayard and Green Road. Excavation at this location has been delayed due to dominion pipeline conflicts.
  • Weather permitting, the week of March 27th, contractor will begin making preparations for the enforcement of the phase one work zone on Green Road from Mayfield to Cedar Rd.
  • Maintenance of traffic signs, barrels and temporary paint lines will be placed restricting two-way traffic to one lane of travel north and south using the eastern one half of the roadway.
  • On or about Monday, April 3rd resurfacing work will begin on the western one half of the roadway.
  • Traffic delays are to be expected during the entire course of construction.

 

February 8, 2023

  • Contractor drilling for and placing concrete foundations (4 each) for future traffic signal poles at the following intersections.
    • Mayfield and Green Rds.
    • Neville and Green Rds.
    • Bayard and Green Rds.

       

  • Road resurfacing is scheduled to begin early 2023 weather permitting.

 