Green Road & Ivanhoe Road
CONTACTS
Contractor: Catts Construction, Inc.
(216) 834-1988
County: Ryan Maver (216) 348-3819
Rich Orosz
DATES
Start Date: 07-01-2022
Notice To Proceed Date: 07-01-2022
Completion Date:
Scheduled Completion Date: 11-30-2022
Anticipated Completion Date: 11-30-2022
AMOUNTS
Project Amount($): 2,974,258.50
Contract Award Amount($): 2,974,258.50
Estimated Cost To Completion($): $2,697,698.10
Approved Contract Increases($):
Approved Contract Decreases($):
PROGRESS

March 17, 2023

Ivanhoe Road

  • Working under temporarily one lane closures, weather permitting, contractor will return to complete various punch list work.
  • New school zone signage including permanent epoxy and thermoplastic paint marking will be installed as warmer weather permits.

     

    Green Road

  • Working under temporarily one lane closures, weather permitting, contractor will return to complete various punch list work.
  • New permanent epoxy and thermoplastic paint marking will be installed as warmer weather permits.
  • Construction of several new drive aprons including a new curb ramp crossing at the North Green Road/Green Road intersection.
  • Re-seeding and mulching as needed for all tree lawn areas.

 

February 8, 2023

Ivanhoe Road

  • Roadway has been resurfaced and full width traffic restored.
  • Signage and permanent striping work will resume as weather permits.
  • Punch list items to be completed in Spring 2023.

     

    Green Road

  • Roadway has been resurfaced and full width traffic restored.
  • Permanent striping work will resume as weather permits.
  • Punch list items to be completed in Spring 2023.

 

November 3, 2022

Ivanhoe Road

  • Traffic signage and stripping (in process)
  • Punch list/ Final clean-up

     

    Green Road-Phase I

  • Two-way traffic  is being maintained between Monticello and Euclid while a southbound only traffic zone is being enforced for Green Road from North Green

     

    Green Road Phase II

  • Contractor will flip traffic zone from phase I to phase II and begin work on the western one half of Green Rd. from Lancaster to North Green Rd. Two-way traffic will be maintained on the newly rehabilitated ester one half section of Green Rd.

     

    The following work will be performed in the next 30 days.

  • Full width surface paving on Green Road from North Green Rd. to Euclid Ave.
  • Remove detour and restore two-way traffic on Green Rd. from North Green Rd., to Euclid Ave.
  • Milling of existing asphalt pavement to a depth of 3” (Landcaster to North Green)
  • Inspect and mark milled surfaces for full depth and partial depth repairs including and deteriorate concrete curbs and sidewalks.
  • Construction of ADA compliant curb ramps at: Blandford, Weston, North Green, and Grouton.
  • Intermediate asphalt paving
  • Inspect, adjust and replace iron on existing manhole, catch basin, and water valves castings.

 

October 3, 2022

  • Ivanhoe Road
    • Final clean-up
    • Surface asphalt paving week of October 10th.
  • Green Road-Phase I (east one half of roadway)
    • Two-way traffic will be maintained between Monticello and North Green Roads while a southbound only traffic zone will be enforced on Green Rd. from north Green Rd. to Euclid Ave.
    • Please follow and obey all detour signs.
  • Phase I     
    • Work continues: Roadway casting adjustments, full depth joint repairs, type 6 curb removal and replacement as directed various drive apron repairs. All work in progress.
  • Phase II
    • West one half of Green Rd. from Landcaster to North Green is scheduled to begin mid to late October.
    • This work will involve the milling 3” of existing asphalt followed by inspection and marking for various partial/full depth repairs.

 

September 12, 2022

  • Ivanhoe Road-Phase II (east one half of roadway)
    • Phase I is completed.
    • Existing asphalt pavement has been planned.
    • Single chip seal treatment applied followed by 1 ¾ of intermediate asphalt pavement.
    • Full depth and partial depth repairs are in process.
    • Various manholes, catch basins, and water valve adjustments continue.
    • Inspection and replacement of type 6 curb and 4’ sidewalks.
  • Green Road-Phase I (east one half of roadway)
    • Two-way traffic will be maintained between Monticello and North Green Roads while a southbound only traffic zone will be enforced on Green Rd. from north Green Rd. to Euclid Ave.
    • Northbound traffic will be detoured to North Green Rd., Cliffview Rd. then to Euclid Ave.
    • Please follow and obey all detour signs.
  • September work will include:
    • Milling top 3’ of existing asphalt, inspection of base pavement for partial and full depth repairs, followed by a single chip seal and placement of intermediate asphalt pavement.

 

August 4, 2022

  • Ivanhoe Road-Phase I (west one half of roadway)
  • Existing asphalt pavement planned
  • Pavement inspected and marked for full depth and partial depth repairs (in progress)
  • Single chip seal treatment.
  • 1 ¾ of intermediate asphalt placement
  • Existing manhole, catch basin, and water valve adjustments to grade using new iron castings (in progress).
  • Inspection and replacement of type 6 curb and 4” sidewalk (in progress).
  • Two-way traffic is being maintained on east one half of Ivanhoe Road.