West Ridgewood Drive - Ridge Road to State Road
CONTACTS
Contractor: Vandra Brothers Const.
(440) 232-3030
County: Darwin Merdes
Patrick Lynch
DATES
Start Date: 05-01-2022
Notice To Proceed Date: 05-01-2022
Completion Date:
Scheduled Completion Date: 11-30-2022
Anticipated Completion Date: 11-30-2022
AMOUNTS
Project Amount($): 2,344,113.87
Contract Award Amount($): 2,344,113.87
Estimated Cost To Completion($): $1,000,000.00
Approved Contract Increases($): 0.00
Approved Contract Decreases($): 0.00
PROGRESS

November 3, 2022

  • Two-way traffic maintained in eastbound lanes.
  • Eastbound lanes repaired including curb and drive aprons. Resurfaced with intermediate course asphalt.
  • Existing asphalt pavement in westbound lanes milled. Base pavement curb, and drive apron repairs in complete.
  • Landscape restoration, partial depth repairs, intermediate course asphalt, casting adjusting in process. 

 

October 3, 2022

  • Two-way traffic maintained in eastbound lanes.
  • Eastbound lanes repaired including curb and drive aprons. Resurfaced with intermediate course asphalt.
  • Existing asphalt pavement in westbound lanes milled. Base pavement curb, and drive apron repairs in process.

 

September 9, 2022

  • Two-way traffic maintained in eastbound lanes.
  • Eastbound lanes repaired including curb and drive aprons. Resurfaced with intermediate course asphalt.
  • Existing asphalt pavement in westbound lanes milled. Base pavement curb, and drive apron repairs in process.

 

August 1, 2022

  • Two-way traffic maintained in westbound lanes.
  • Pavement repairs, curb replacement completed as well as intermediate course asphalt in eastbound lanes.

 

July 7, 2022

  • Two-way traffic maintained in westbound lanes
  • Existing asphalt surface in eastbound lanes has been milled off.
  • Removal and replacement of deteriorated pavement and curb continues along with adjusting and reconstructing existing castings.