Construction Updates

Wolf Road Resurfacing & Widening
CONTACTS
Contractor: Catts Construction, Inc.
(440) 834-1988
County: Michael Cotter (216) 280-8757
Robert Willis (216) 762-9493
DATES
Start Date: 05-01-2022
Notice To Proceed Date: 05-01-2022
Completion Date:
Scheduled Completion Date: 08-01-2023
Anticipated Completion Date: 05-01-2023
AMOUNTS
Project Amount($): 4,714,327.77
Contract Award Amount($): 4,714,327.77
Estimated Cost To Completion($):
Approved Contract Increases($):
Approved Contract Decreases($):
PROGRESS

November 3, 2022

Work completed in the last weeks

  • New type 6 curb placement
  • Surface course paving
  • Castings adjustments
  • Full depth repairs
  •  

    Upcoming Work

  • Final striping new signage installation

 

July 11, 2022

  • Removed pavement to begin work on proposed bike lane.
  • Placed new underdrain
  • Placed traffic compacted surface
  • Sidewalk removals
  • Driveway apron removals.

    Upcoming
  • Pavement planning
  • Sidewalk replacements.