Construction Updates

St. Clair Ave. Bridge Rehabilitation Over Doan Creek City of Cleveland
CONTACTS
Contractor: Chagrin Valley Paving, Inc.
(216) 556-3932
County: Ryan Maver (216) 556-3932
Brian Vigh (216) 301-9010
DATES
Start Date: 05-01-2021
Notice To Proceed Date: 06-01-2021
Completion Date: 05-01-2022
Scheduled Completion Date: 05-01-2022
Anticipated Completion Date: 05-01-2022
AMOUNTS
Project Amount($): $1,976,777.57
Contract Award Amount($): $1,976,777.57
Estimated Cost To Completion($): $1,458,993.77
Approved Contract Increases($): $59,882.56
Approved Contract Decreases($): 0.00
PROGRESS
November 8, 2022
  • No work zone has been established; St Clair is completely open to normal traffic pattern.
  • Chagrin Valley has ceased work as of 7/15/22.
  • Project is not complete.
  • Contractor has resumed work as of 10/28/22

October 3, 2022
  • No work zone has been established. St. Clair is completely open to normal traffic pattern.
  • Chagrin Valley ceased work as of 7/15/22. Project is not complete.

September 9, 2022
  • No work zone has been established; St Clair is completely open to normal traffic pattern.
  • Chagrin Valley has ceased work as of 7/15/22.
  • Project is not complete.

July 7, 2022
  • No work zone has been established; St Clair is completely open to normal traffic pattern.
  • Chagrin Valley has returned to work as of 6-20-22. Work has begun on building liner panels in preparation for installation of arch liner.

June 2, 2022
  • No work zone has been established; St Clair is completely open to normal traffic pattern.
  • Work has ceased on the project for the month due to Chagrin Valley and their sub–Grout Systems.

May 5, 2022
  • Work has ceased on the project for the month due to Chagrin Valley and their su-Grout Systems.
  • No work zone has been established. St. Clair is completely open to normal traffic pattern.

April 15, 2022
  • Work has ceased on the project for the month due to Chagrin Valley and their su-Grout Systems.
  • No work zone has been established. St. Clair is completely open to normal traffic pattern.

March 2, 2022
  • No work has ben established; St Clair is completely open to normal traffic pattern. Work has ceased on the project for the month due to Chagrin Valley and their sub - Grout Systems.
December 9, 2021
  • Proposed concrete invert installed (90% complete).
  • Formed and poured knee wall on east wall of bridge.
  • Repaired gabion baskets on the rear slope of the bridge.
  • Preparation beginning for removal of existing wingwall.

November 8, 2021
  • Proposed concrete invert installed (90% complete).
  • Formed and poured knee wall on west wall of bridge.
  • Current work is being done to form and pour the knee on the east wall of the bridge.

October 7, 2021
  • A 12” pump is on site bypassing waterflow for work on existing invert.
  • Approximately 2/3 of the existing invert has been removed and unclassified excavation as per the plan was performed.
  • An additional 12” pump was being brough to project to assist in the work for the invert.
  • Current work is being done to place stone, steel reinforcement, and concrete for the invert removed thus far.

July 6, 2021
  • Trees on the project were previously cut down by CCDPW.
  • Contractor has been working on removing trees from the project and waiting for placement of the required CL fence to be installed around the project.
  • No work zone has been established; St. Clair is completely open to normal traffic pattern.
  • Current work consists of full depth removal and rigid replacement of pavement identified for repair in northbound, center lines.

June 2, 2021
  • Scheduled start date of this project is June 7, 2021.