Construction Updates

Memphis Road Replacement
CONTACTS
Contractor: Independence Excavating, Inc
(440) 891-1444
County: Memphis Road (216)280-8757
Robert L. Willis (216)762-9493
DATES
Start Date: 03-01-2020
Notice To Proceed Date: 07-01-2020
Completion Date: 07-01-2023
Scheduled Completion Date: 07-01-2023
Anticipated Completion Date: 04-01-2023
AMOUNTS
Project Amount($): $5,853,453.30
Contract Award Amount($): $5,853,453.30
Estimated Cost To Completion($): 0
Approved Contract Increases($): 0
Approved Contract Decreases($): 0
PROGRESS

November 3, 2022

Work completed in the last weeks

  • Beam placement
  • 302 asphalt base pavements
  • Intermediate paving

     

    Upcoming Work

  • Bridge deck pour
  • Parapet and sidewalk pour
  • Diaphragm pour
  • Approach slabs pour

July 11, 2022

  • Existing super structure demolished under force account.
  • Demolition of substructure in the upcoming weeks.

March 17, 2022

  • Work zone signage and traffic devices are to be set up and used for the implementation of detour route during sequenced construction phasing.
  • Begin installation of falsework over the CSX Railroad and then the demolition of the existing structure.
December 13, 2021

Work Completed:
  • Utility relocation over the CSX Railroad
  • Maintain erosion control.
Work to be Performed:
  • Beginning of January work is to resume (tentative Date January 3, 2022).
  • Work zone signage and traffic devices are to be set up and used for the implementation of detour route during sequenced construction phasing.
  • Begin installation of falsework over the CSX Railroad and then the demolition of the existing structure.
June 4, 2021

Work Completed:
  • Completed the relocation and installation of the new 36” waterline.
  • Installed new concrete retaining wall.
  • Utility relocation over the CSX Railroad Maintain erosion control.
Work to be Performed:
  • Continue utility relocation over the CSX Railroad.