Construction Updates

Cedar Point Bridge 00.49
CONTACTS
Contractor: Union Industrial Contractors
(440)998-7871
County: Calvin Overmyer 440-455-1171
Joe Charif 216-701-1262
DATES
Start Date: 06-01-2021
Notice To Proceed Date: 06-01-2021
Completion Date:
Scheduled Completion Date: 10-01-2022
Anticipated Completion Date: 10-01-2023
AMOUNTS
Project Amount($):
Contract Award Amount($): 3,055,480.60
Estimated Cost To Completion($): 3,055,480.60
Approved Contract Increases($): 0
Approved Contract Decreases($): 0
PROGRESS
October 6, 2022
  • This project continues to be under suspension, pending engineering review and re-design.

 

September 15, 2022
  • The bridge will remain closed with a revised completion of summer 2023, subject to material availability and supply chain issues that many industries are facing at this time.
  • Construction began on the Cedar Point Road bridge over the Rocky River in North Olmsted in the fall of 2021 and has remained closed for construction activities since that time.
  • Recently, there has been a pause in construction activity to evaluate the best path moving forward concerning the necessary replacement of the interior beams of the subject structure.
  • During the systematic repair of all the concrete bridge beams, it became clear that the interior beams displayed a larger and deeper extent of deterioration than originally anticipated. The project team, including the designer, contractor, the County and ODOT, are currently developing a plan to complete the construction of the bridge in a cost-effective manner that will provide a maximum service life for the future structure.

 

June 3, 2022
  • The project is currently in the demolition phase.
  • Access to the bridge and Little Cedar Point Picnic Area is closed to the public
  • Access to Frostville Museum and Farmer’s Market remain open.
  • Detours are posted.

 

March 2, 2022
  • The project is currently in the demolition phase.
  • Access to the bridge and Little Cedar Point Picnic Area is closed to the public
  • Access to Frostville Museum and Farmer’s Market remain open.
  • Detours are posted.

 

December 10, 2021
  • The bridge is closed to all traffic.
  • Demolition work continues.
  • Maintenance of traffic and detour are in effect.