Due to routine maintenance, sites may be unavailable on Sunday June 11 between 8 AM and 10 AM. 

Department of Public Works


Construction Updates

Memphis Road Replacement
CONTACTS
Contractor: Independence Excavating, Inc
(440) 891-1444
County: Michael Cotter (216) 280-8757
Robert L. Willis (216)762-9493
DATES
Start Date: 03-01-2020
Notice To Proceed Date: 07-01-2020
Completion Date: 07-01-2023
Scheduled Completion Date: 07-01-2023
Anticipated Completion Date: 04-01-2023
AMOUNTS
Project Amount($): $6,428,419.16
Contract Award Amount($): $5,853,453.30
Estimated Cost To Completion($): 0
Approved Contract Increases($): $574,965.86
Approved Contract Decreases($): 0
PROGRESS

June 2, 2023

Work completed in the last weeks.

  • Grout Matting Installation
  • Final restoration
  • Final Striping

     

    Upcoming Work

  • Punch list itemsl

 

May 19, 2023

Work completed in the last weeks.

  • Bridge sealing and painting.
  • Grout mat slope protection installation.

     

    Upcoming Work

  • Grout matting installation
  • Final restoration
  • Final striping.

 

May 4, 2023

Work completed in the last weeks.

  • Bridge sealing and painting.
  • Grout mat slope protection installation.

     

    Upcoming Work

  • Grout matting installation
  • Final restoration
  • Final striping.

 

February 6, 2023

Work completed in the last weeks.

  • Bridge parapet
  • Topsoil and winter seeding
  • Guardrail and vandal fence installation

Upcoming Work

Grout matting (Spring 2023)

 

January 6, 2023

Work completed in the last weeks

  • Bridge deck placement
  • Approach slab placement
  • Diaphragm placement
  • Sidewalk placement

     

    Upcoming Work

  • Bridge parapet
  • Grout matting pour
  • Topsoil and winter seeding
  • Guardrail and vandal fence installation.

 

November 3, 2022

Work completed in the last weeks

  • Beam placement
  • 302 asphalt base pavements
  • Intermediate paving

     

    Upcoming Work

  • Bridge deck pour
  • Parapet and sidewalk pour
  • Diaphragm pour
  • Approach slabs pour

 

July 11, 2022

  • Existing super structure demolished under force account.
  • Demolition of substructure in the upcoming weeks.

 

March 17, 2022

  • Work zone signage and traffic devices are to be set up and used for the implementation of detour route during sequenced construction phasing.
  • Begin installation of falsework over the CSX Railroad and then the demolition of the existing structure.

 

December 13, 2021

Work Completed:

  • Utility relocation over the CSX Railroad
  • Maintain erosion control.

Work to be Performed:

  • Beginning of January work is to resume (tentative Date January 3, 2022).
  • Work zone signage and traffic devices are to be set up and used for the implementation of detour route during sequenced construction phasing.
  • Begin installation of falsework over the CSX Railroad and then the demolition of the existing structure.

 

June 4, 2021

Work Completed:

  • Completed the relocation and installation of the new 36” waterline.
  • Installed new concrete retaining wall.
  • Utility relocation over the CSX Railroad Maintain erosion control.

Work to be Performed:

  • Continue utility relocation over the CSX Railroad.



Discover Veterans Bridge logo

Veterans Memorial Bridge Weekend

Bridge and Subway Tours are back, as well as an open dialogue about future use of the underside of the bridge, moving forward. June 23-24, 2023.

Find out more