Start Date: 03-01-2020
Notice To Proceed Date: 07-01-2020
Completion Date:
07-01-2023
Scheduled Completion Date: 07-01-2023
Anticipated Completion Date: 04-01-2023
Project Amount($): $6,428,419.16
Contract Award Amount($): $5,853,453.30
Estimated Cost To Completion($): 0
Approved Contract Increases($): $574,965.86
Approved Contract Decreases($): 0
June 2, 2023
Work completed in the last weeks.
- Grout Matting Installation
- Final restoration
- Final Striping
Upcoming Work
- Punch list itemsl
May 19, 2023
Work completed in the last weeks.
- Bridge sealing and painting.
- Grout mat slope protection installation.
Upcoming Work
- Grout matting installation
- Final restoration
- Final striping.
May 4, 2023
Work completed in the last weeks.
- Bridge sealing and painting.
- Grout mat slope protection installation.
Upcoming Work
- Grout matting installation
- Final restoration
- Final striping.
February 6, 2023
Work completed in the last weeks.
- Bridge parapet
- Topsoil and winter seeding
- Guardrail and vandal fence installation
Upcoming Work
Grout matting (Spring 2023)
January 6, 2023
Work completed in the last weeks
- Bridge deck placement
- Approach slab placement
- Diaphragm placement
- Sidewalk placement
Upcoming Work
- Bridge parapet
- Grout matting pour
- Topsoil and winter seeding
- Guardrail and vandal fence installation.
November 3, 2022
Work completed in the last weeks
- Beam placement
- 302 asphalt base pavements
- Intermediate paving
Upcoming Work
- Bridge deck pour
- Parapet and sidewalk pour
- Diaphragm pour
- Approach slabs pour
July 11, 2022
- Existing super structure demolished under force account.
- Demolition of substructure in the upcoming weeks.
March 17, 2022
- Work zone signage and traffic devices are to be set up and used for the implementation of detour route during sequenced construction phasing.
- Begin installation of falsework over the CSX Railroad and then the demolition of the existing structure.
December 13, 2021
Work Completed:
- Utility relocation over the CSX Railroad
- Maintain erosion control.
Work to be Performed:
- Beginning of January work is to resume (tentative Date January 3, 2022).
- Work zone signage and traffic devices are to be set up and used for the implementation of detour route during sequenced construction phasing.
- Begin installation of falsework over the CSX Railroad and then the demolition of the existing structure.
June 4, 2021
Work Completed:
- Completed the relocation and installation of the new 36” waterline.
- Installed new concrete retaining wall.
- Utility relocation over the CSX Railroad Maintain erosion control.
Work to be Performed:
- Continue utility relocation over the CSX Railroad.